Scaffold Tower Integration

Before Erecting the Tower 

  • Check all components are in good condition. 

  • Check wheels for effective rotation. 

  • Check brakes and locking devices work correctly. 

  • Before erecting a tower on a suspended floor, ensure the bearing capacity of the floor is sufficient for the planned load. 

Before Use 

  • Ensure the tower is vertical and square. 

  • Towers must not be used unless the wheels are locked. 

  • Check that outriggers are set correctly and secured. 

  • Ensure the platform is fully boarded out and that guardrails and toe boards are fitted if the working platform is over 2 metres high. 

  • The gap between toe boards and mid guardrails, and between mid and top guardrails, must not exceed 470 mm. 

Stability 

  • Never climb up the outside of a tower. Use the stairway or ladder on the inside. 

  • Follow the manufacturer’s instructions on base-to-height ratio. 

  • Hoist materials up from the inside of the tower. 

  • Do not move the tower if people or materials are still on the platform. 

  • Do not pull the tower along while standing on it. 

  • Towers must only be used on firm, flat surfaces.